Draw the activity-on-node aon project network associated


Problem 1)

Activity

Immediate
Predecessor(s)

Time
(Days)

A

-

3

B

A

4

C

A

6

D

B

6

E

B

4

F

C

4

G

D

6

H

E,F

8

Draw the activity-on-node (AON) project network associated with the above activities.

How long should it take the team to complete this project? _______________

To determine this - do a forward and backward pass

Each activity will have an ES, EF, LS, LF, and Slack value.

Activity

Time (Days)

ES

EF

LS

LF

Slack

A

3

 

 

 

 

 

B

4

 

 

 

 

 

C

6

 

 

 

 

 

D

6

 

 

 

 

 

E

4

 

 

 

 

 

F

4

 

 

 

 

 

G

6

 

 

 

 

 

H

8

 

 

 

 

 

Problem 2) Draw the AON network and answer the following questions:

a) What is the expected time for activity C?___

b) What is the variance for activity C?____

c) Based on the calculation of estimated times, what is the critical path?___

d) What is the estimated time of the critical path?___

e) What is the variance of the critical path?___

f) What is the probability of completion of the project before Week 36?___

Time Estimates (in weeks)

Activity

Immediate
Predecessor(s)

Opt.

Most
Likely

Pess.

Te

Var

Slack

A

-

4

8

10

 

 

 

B

A

2

8

24

 

 

 

C

A

8

12

16

 

 

 

D

A

4

6

10

 

 

 

E

B

1

2

3

 

 

 

F

E, C

6

8

20

 

 

 

G

E, C

2

3

4

 

 

 

H

F

2

2

2

 

 

 

I

F

6

6

6

 

 

 

J

I), G, H

4

6

12

 

 

 

K

I, J

2

2

3

 

 

 


Round to the tenths place.

Network Diagram: Should be legible and flow from left to right