Label
|
Work Element
|
Precedence
|
Time (Min)
|
A
|
Align Frame on Workstation
|
-
|
4.2
|
B
|
Assemble Handle Bar
|
A
|
2.2
|
C
|
Assemble Gears and Pedals
|
A
|
2.4
|
D
|
Assemble Wheels
|
C
|
1.5
|
E
|
Tune the bicycle
|
B, D
|
1.8
|
Assume that the assembly line runs 40 hours per week.
Draw out the assignment of tasks to workstations in a diagram with labels. There may be a couple possible layouts so choose the one with the highest potential output
(Hint: you will need this to see the bottleneck workcenter, which determines the actual cycle time).
What is the efficiency of this assembly line?