Draw any network diagram which shows the precedence


Assignment: Critical Chain Scheduling

Consider the following network diagram information

Task

Predecessor

Duration (weeks)

A

 

3

B

A

5 (4)

C

A

4 (3)

D

B

1

E

C, D

2

(a) Draw any network diagram which shows the precedence relationship and Identify the critical path and the length of it.

(b) Suppose that the task B and task C are performed by the same resource (only one unit), and it has been decided that the task B is going to be conducted earlier than the task C - this creates a new precedence relationship between B and C due to the resource. The new duration by the single unit is 4 and 3 for B and C, respectively. Now identify the critical path again here - This new critical path may be called a critical chain if we assume that this reduced task duration is very aggressive compared to previous task durations.

(c) Consider the new critical path obtained in part (b) as a critical chain. Then, draw a network diagram to show the critical chain with project buffer(s) and feeding buffer(s) - you do not need to describe the duration of buffers.