Assignment: Critical Chain Scheduling
Consider the following network diagram information
Task
|
Predecessor
|
Duration (weeks)
|
A
|
|
3
|
B
|
A
|
5 (4)
|
C
|
A
|
4 (3)
|
D
|
B
|
1
|
E
|
C, D
|
2
|
(a) Draw any network diagram which shows the precedence relationship and Identify the critical path and the length of it.
(b) Suppose that the task B and task C are performed by the same resource (only one unit), and it has been decided that the task B is going to be conducted earlier than the task C - this creates a new precedence relationship between B and C due to the resource. The new duration by the single unit is 4 and 3 for B and C, respectively. Now identify the critical path again here - This new critical path may be called a critical chain if we assume that this reduced task duration is very aggressive compared to previous task durations.
(c) Consider the new critical path obtained in part (b) as a critical chain. Then, draw a network diagram to show the critical chain with project buffer(s) and feeding buffer(s) - you do not need to describe the duration of buffers.