Consider the activity list in the table below. All duration estimates or estimated times are in days.
- Draw an AOA network diagram representing the project. The network should proceed from Node 1 to Node 9. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.
- Identify all of the paths on the network diagram and note how long they are.
- What is the critical path for this project and how long is it?
- What is the shortest possible time needed to complete this project?