Draw an activity-on-arrow diagram for the project


Consider the project described:

Activity

Immediate

Predecessors

Normal

Time

Normal Cost

Crash Time

Crash Cost

A

-

6

100

6

100

B

A

10

2,000

4

2,600

C

A

10

800

8

920

D

B

6

700

5

  750 ...

E

B

8

1,000

6

1,140

F

C,D

9

1,400

7

1,550

G

E

14

3,000

10

3,320

H

E, F

10

900

8

1,020

a) Draw an activity-on-arrow diagram for the project.

b) Using the normal activity times (in weeks), carry out the forward and the backward pass calculations. Identify the critical path (A-B-D-F-H), the total project time and total normal project cost.

c) Determine which activities to crash and by how much to achieve a project completion time of 36 weeks at minimum cost. Provide a crash table.

Solution Preview :

Prepared by a verified Expert
Project Management: Draw an activity-on-arrow diagram for the project
Reference No:- TGS01956383

Now Priced at $20 (50% Discount)

Recommended (91%)

Rated (4.3/5)