Question A:
A project is made of 7 activities:
Activity
|
Initiation
|
Analysis
|
Data Modeling
|
Process Modeling
|
Design
|
Feasibility Analysis
|
Documentation
|
a
|
14
|
14
|
3
|
1
|
2
|
4
|
5
|
b
|
18
|
34
|
11
|
1
|
4
|
12
|
15
|
m
|
16
|
15
|
4
|
1
|
3
|
5
|
13
|
Predecessors
|
--
|
--
|
Analysis
|
Analysis
|
Data and Process Modeling
|
Data and Process Modeling
|
Initiation and Analysis
|
- Draw an A on A chart.
- Find the critical path and the project duration.
Question B
A project is made of 8 activities:
Activity
|
A1
|
A2
|
A3
|
A4
|
A5
|
A6
|
A7
|
A8
|
Duration
|
20
|
13
|
15
|
9
|
20
|
30
|
20
|
25
|
Pre. Activity
|
-
|
-
|
-
|
A2
|
A1,A3,A4
|
A1,A3,A4
|
A5,A6
|
A6
|
- Draw an A on A chart.
- What is the critical path? What is the project duration?
- When the latest can we start activity A1?
- When the latest can we start activity A5?
- Refer to the critical path you found in b. Assume that every activity is normally distributed. Each activity's mean is given in the table above. Each activity's standard deviation is 20% of its mean (for example, the mean duration of activity A2 is 13 and its standard deviation is 2.6). What is the probability that the project will last more than 80 days?
Question C
Complete the following table:
slack
|
LF
|
LS
|
EF
|
ES
|
Predecessor(s)
|
Duration
|
Task
|
|
|
|
|
|
-
|
5
|
A
|
|
|
|
|
|
-
|
10
|
B
|
|
|
|
|
|
A
|
20
|
C
|
|
|
|
|
|
A,B
|
13
|
D
|
|
|
|
|
|
C,D
|
10
|
E
|
|
|
|
|
|
A,B
|
25
|
F
|
|
|
|
|
|
E,F
|
8
|
G
|