Problem:
Question 1) Draw an Activity-on-Node Diagram, identify activity duration, slack for each activity, project duration, and project critical path for the following:
Activity Name
|
Predecessor(s)
|
a
|
m
|
b
|
A
|
None
|
5
|
30
|
40
|
B
|
None
|
10
|
20
|
50
|
C
|
None
|
5
|
15
|
30
|
D
|
A
|
5
|
10
|
30
|
E
|
B,C
|
15
|
20
|
25
|
F
|
C,D
|
15
|
20
|
60
|
G
|
F
|
10
|
20
|
50
|
Solve the problem and show all work.