QUESTION 1:
- Tallahassee Company is considering an investment in a high-quality blueprint printerwith the following cash flows:
YEAR
|
INVESTMENT/CEDIS
|
CASH INFLOW/CEDIS
|
1
|
(38000)
|
2000
|
2
|
(6000)
|
4000
|
3
|
|
8000
|
4
|
|
9000
|
5
|
|
12000
|
6
|
|
10000
|
7
|
|
8000
|
8
|
|
6000
|
9
|
|
5000
|
Required:
i) Determine the payback period of the investment.
ii) Would the payback period be affected if the cash inflow in year 8 was18,000Cedis?
- Given the expected net cash flow of projects X and Y in the table below, answer the questions that follow:
YEAR
|
PROJECT X
|
PROJECT Y
|
0
|
(10000)
|
(10000)
|
1
|
6500
|
3500
|
2
|
3000
|
3500
|
3
|
3000
|
3500
|
4
|
1000
|
3500
|
Required:
i. Calculate for each, the payback period, net present value (NPV),and profitability index (PI). Use 10% discount rate.
ii. Should both projects be accepted if they are interdependent?
iii. Which project should be accepted if they are mutually exclusive?
QUESTION 2:
Given the table below, calculate the EXPECTED VALUE OF PERFECT INFORMATION (EVPI) and EXPECTED OPPORTUNITY LOSS (EOL) using maximization approach. What is the relation between EVPI and EOL?
NB.: di=decision alternative, Si=states of nature, and probabilities are probabilities of state of nature.
|
s1
|
s2
|
s3
|
d1
|
6
|
5
|
3
|
d2
|
1
|
4
|
7
|
d3
|
3
|
8
|
9
|
Probability
|
0.4
|
0.1
|
0.5
|
QUESTION 3:
What is the difference between operational and technical feasibility? At the project planning phase, detailed plans are made to help complete the project successfully. Name 8 of them and explain. Name three main ways of IT project deployment. What does project close entails?
QUESTION 4:
a. What is a project? State 3 attributes of a project.
b. When is a project said to be successful?
c. What is the project management life cycle?
d. In determining project feasibility at the initiation stage or phase, list 3 out of the many factors to consider.
e. List 4 causes of project failure at the initiation stage?
f. Name 6 members of the project team that are assembled at the planning stage.
QUESTION 5:
A project consists of eight activities whose durations are as follows:
Activity
|
A
|
B
|
C
|
D
|
E
|
F
|
G
|
H
|
Duration
|
2
|
3
|
5
|
6
|
1
|
3
|
1
|
7
|
The precedence relations are as follows:
B must follow A
C must follow B
D must follow A, B and C
E must follow D
F must follow C
G must follow E and F
H must follow E and G
QUESTIONS
a. Draw a project network
b. Develop the activity schedule for the project
c. Identify the critical path
d. What is the expected completion time for the project?