Given the following information, draw CPM diagram:
Activity Immediate Predecessor Duration (Days)
1 - 5
2 - 3
3 1, 4 2
4 2 6
5 2 5
6 3, 5 3
a) Draw a network diagram and show the critical path.
b) What is the earliest time, the above project can be completed?