Draw a gantt chart showing completion time values


Problem: A production line consists of two main workstations: an assembly workstation and a packaging workstation. The processing times for 11 jobs (in minutes) that must be processed on these two workstations are given below. There is plenty of space in between the workstations such that blocking does not occur. Find the optimal job sequence for this serial system with the minimum makespan. Make sure you show the steps you take to find an optimal solution. Draw a Gantt chart that shows completion time values.

Job                    J1    J2     J3    J4    J5     J6     J7    J8    J9    J10   J11
Workstation 1     30    18    28    22    46    16    20    5    15    25    34
Workstation 2     10    20    12    14    24    26    32    6    20    10    25.