Draw a critical path diagram sometimes referred to as pert


Assignment- Critical Path Diagram

For a project with the following tasks, durations, and task precedence data:

• Draw a Critical path diagram. Sometimes referred to as PERT or a CPM diagram.
• How long will the project take to complete.

 

Task Description

Duration (days)

Preceding Task

1

Requirements Collection

5

-

2

Screen Design

6

1

3

Report Design

6

1

4

Database Design

2

2,3

5

User Documentation

5.5

4

6

Programming

5

4

7

Testing

3

6

8

Installation

1

5,7

Solution Preview :

Prepared by a verified Expert
Project Management: Draw a critical path diagram sometimes referred to as pert
Reference No:- TGS02255494

Now Priced at $25 (50% Discount)

Recommended (92%)

Rated (4.4/5)