Problem
Assume the source selection criteria for evaluating proposals for a project is as follows:
a) Management approach - 15%
b) Technical approach - 15%
c) Past performance - 20%
d) Price - 20%
e) Interview results and samples - 30%
Use Figure 6-26 as a guide and the supplier evaluation matrix template from the companion website to calculate the total weighted scores for three proposals. Enter ratings for Proposal 1 as 80, 90, 70, 90, and 80, respectively. Enter ratings for Proposal 2 as 90, 50, 95, 80, and 95. Enter ratings for Proposal 3 as 60, 90, 90, 80, and 65. Add a paragraph summarizing the results and your recommendation on the spreadsheet.