Assignment:
(Electronics Engineer) Concerned project lead time is too high, management is considering the purchase of a new electronics design software package they believe will enhance Sadie's productivity. Suppose they purchase the new software and 5. find Sadie's average time to complete an individual job drops from 1 week to 0,8 week (4 days). Assume the new software has no impact on the variability of the time it takes Sadie to complete an individual job. Suppose management does not increase the number of jobs (arrival rate) Sadie has to do. After adopting the software, what will be Sadie's new average lead time?