1.Hart Manufacturing operates an automated steel fabrication process. For one operation, Hart has found that 45% of the total throughput (manufacturing cycle) time is spent on non-value-added activities. Delivery cycle time is 12 hours, waiting time during the production process is 3 hours, queue time prior to starting the production process is 2 hours, and inspection time is 1.2 hours. What is the move time recorded for the operation?
A. 0.85 hours
B. 6.5 hours
C. 5.8 hours
D. 1.5 hours T
2.The manufacturing cycle efficiency (MCE) for this operation is:
A. 55%
B.45%
C. 35%
D. 65%
3.What is the throughput (manufacturing cycle) time for the operation?
A. 12.0 hours
B. 10.0 hours
C. 5.8 hours
D. 9.0 hours