Problem
ABC uses a standard costing system in connection with the manufacture of a "one size fits all" article clothing. Each unit of finished product contains 2 yards of direct materials. However, a 20% direct material spoilage calculated on input quantities occurs during the manufacturing process. The cost of the direct material is P3 per yard. The standard direct material cost per unit of finished product is (up to two decimal places).