Problem:
The Analytic Hierarchy Process (AHP) is being employed in a project selection decision of three projects A, B, and C. The total score for project A is 0.650; for project B is 0.514; and for project C is 0.321. Which of the following statements is best?
1. Project A is as good as project C.
2. The analysis must be incorrect because the total scores must sum to 1.00.
3. The analysis must be incorrect because two total scores exceed 0.50.
4. The analysis must be incorrect because the Project C's score is odd.