Discuss calculations for es-ef-ls and total float


Discuss the below:

Problem Sets in Planning and Scheduling

Fence schedule. This deliverable requires that you assign durations for each activity and must have (1) a network diagram with clear labeling; (2) calculations for ES, EF, LS, LF, and total float; and (3) a red line that clearly marks/identifies the critical path.

Planter schedule. This deliverable requires that you assign durations for each activity and must have (1) a network diagram with clear labeling; (2) calculations for ES, EF, LS, LF, and total float; and (3) a red line that clearly marks/identifies the critical path.

Update: Durations have been added

FENCE PROJECT
Activity Activity Description Predecessor Duration
A Mobilize
2
B Clearing and grubbing A 2
C Layout fence B 2
D Deliver posts C 1
E Auger post holes C, D 3
F Set posts in holes D, E 3
G Backfill and plumb posts F 2
H Deliver boards for fence G 1
I Install boards for fence H 3
J Paint fence H 2
K Plant shrubs along fence I, J 3
L Final inspection K 1
M Demobilize L 2
PLANTER PROJECT
Activity Activity Description Predecessor Duration
A Mobilize
2
B Install security fence A 2
C Excavate planter foundation A,B 4
D Set forms B,C 3
E Set rebar D 3
F Order concrete E 1
G Place concrete F 1
H Strip forms G 3
I Deliver bricks to site G,H 1
J Construct masonry planter I 4
K Place soil in planter J 2
L Remove security fence K 2
M Demobilize L 2

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Discuss calculations for es-ef-ls and total float