Discuss a critical path and project duration


Discussion:

1) Draw the Network showing the length of each path and performing forward and backward passes giving ES,EF,LS, & LF in the box for each activity

2) Your staff has found a way to reduce the time to do activity H to 4 months. What will the effect be on the critical path and Project Duration if H is reduced to 4 mos?

3) Given crash costs in the last column which activity should be crashed for 1 month 1st?

Use this format for the activities boxes

Activity
ES LS

Duration EF LF
Slack

Activity

Preceding

Activity

Duration months

Cost to Crash   1st Month

Start

 

0

 

D

Start

4

$1,000

A

Start

3

$1,200

F

D, A

7

$1,300

E

D

8

$1,400

G

F, E

5

$1,500

H

F

5

$1,600

B

G

7

$1,700

C

B

8

$1,800

End

C, H

0

 

Request for Solution File

Ask an Expert for Answer!!
Other Subject: Discuss a critical path and project duration
Reference No:- TGS01825720

Expected delivery within 24 Hours