Direct labor cost variance


Question 1: Barbados has prepared the given standard cost information for its product Zeta:

Raw material    50 kg @2.5         125
Direct labor     14 hrs @ 4.75      66.50

Actual results for the period were recorded as shown below:

Production                                      150 units
Direct material purchased                7,000 kg @ a cost of Rs 18,200
Opening stock direct materials         1,300 kg
Closing stock direct materials           850 kg
Wages paid for 2020 hrs                 9898

Required:

A) Compute:

a) Direct labor cost variance, analyzed into rate and efficiency variances.
b) Direct material cost variance, analyzed into price and usage variances.

B) In brief describe three of the causes of material price variance and labor rate variance.

Question 2:

A) In brief describe, supported by one illustration for each, what you understand by the given types of cost:

a) Variable cost
b) Fixed cost
c) Step cost

B) In brief explain four qualities of good accounting information.