Question:
Developing and Using a Predetermined Overhead Rate
Assume that the following predictions were made for 2009 for one of the plants of Milliken & Company:
Total manufacturing overhead for the year
|
$44,000,000
|
Total machine hours for the year
|
2,000,000
|
Actual results for February 2009 were as follows:
Manufacturing overhead
|
$5,480,000
|
Machine hours
|
310,000
|
(a) Determine the 2009 predetermined overhead rate per machine hour.
(b) Using the predetermined overhead rate per machine hour, determine the manufacturing overhead applied to Work-in-Process during February.
(c) As of February 1, actual overhead was under applied by $500,000. Determine the cumulative amount of any over applied or under applied overhead at the end of February.