Assignment:
Coleman Rich, Ltd., has received the following orders:
Period |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
Order Size |
60 |
30 |
10 |
40 |
70 |
10 |
40 |
30 |
40 |
0 |
The entire fabrication for these units is scheduled on one machine. There are 2,250 usable minutes in a week, and each unit will take 65 minutes to complete. Develop a capacity plan, using lot splitting, for the 10-week time period.
Provide complete and step by step solution for the question and show calculations and use formulas.