Develop risk mitigation plans


Assignment:

Risks: If a senior artist retires before the movie is complete, the production of art renderings will be delayed and

will result in slipping the project schedule. Likelihood: Moderate; Consequence: Major If there is an earthquake in Burbank, CA, all electronic files on the computers in the building will not be

accessible either temporarily or permanently and will result in stopping work on the movie. Likelihood:

Slight; Consequence: Major If the actor's union goes on strike, the audio portion of the movie will get affected, resulting in a delay in the

schedule. Likelihood: Strong; Consequence: Major If the parent organization sells the building where the project works, the project will have to move, resulting

in a day-for-day schedule slip. Likelihood: Slight; Consequence: Moderate

Opportunities: If new software becomes available for the key animation process, the project will be able to complete the

artistic animation quicker, resulting in delivering that portion of the project earlier. If you can convince another production project within your company to share a screening room, you could

reduce the project space requirement and save $15,000 in overhead expenses.

Develop risk mitigation plans to address each of these risks, and a plan to enhance the opportunity. You may find

that more than one risk mitigation strategy is available for any given risk. Make sure to indicate the risk or

opportunity strategy-avoid, transfer, mitigate, accept, exploit, share, and enhance.

Submission Requirements:
Write your answers in at least 2-3 pages. in the

APA format. Font: Arial, 12-point, and double-spaced.

Solution Preview :

Prepared by a verified Expert
Microeconomics: Develop risk mitigation plans
Reference No:- TGS01809813

Now Priced at $30 (50% Discount)

Recommended (91%)

Rated (4.3/5)