Problem
Develop your critical elements to support a completed RFP suitable for submission to vendors.
You are a general contractor wishing to put up a modest-sized concrete production plant on the outskirts of town. The plant would operate on only one 10-hour shift per day and would produce about 400 cubic yards of output per day for 6 days per week. It is necessary for an environmental impact study to be undertaken before the county can issue a permit. The biggest issue is, of course, the air quality implications of concrete production, but potential impacts on water quality are of concern as well. It is now October, and you want to start building the plant by the end of next summer, if at all possible. It is now time to issue an RFP to procure an environmental impact analysis. Studies of this type normally require about 3 months of concerted effort by a team of analysts.