Put components for Part 1 of assignment here:
Develop an in-depth schedule for your initial project based on the Work Breakdown Structure you have completed in Unit III. Please refer to the "INTEGRATED PROJECT: Developing the Project Schedule" Be sure to include-
1. An activity precedence diagram
2. An activity duration table
3. A network diagram and Gannt charts
Exercise 1
Suppose we have a complete activity predecessor table (shown below) and we wish to create a network diagram highlighting the activity sequence for this project. Using MS Project, enter the activities, their durations, and their predecessors for activities A through E. Note that all duration times are in days.
Project: Remodeling an Appliance
|
Activity
|
|
Duration
|
Predecessors
|
A
|
Conduct competitive analysis
|
3
|
|
B
|
Review field sales reports
|
2
|
|
C
|
Conduct tech capabilities assessment
|
5
|
|
D
|
Develop focus group data
|
2
|
A, B, C
|
E
|
Conduct telephone surveys
|
3
|
D
|
F
|
Identify relevant specification improvements
|
3
|
E
|
G
|
Interface with marketing staff
|
1
|
F
|
li
|
Develop engineering specifications
|
5
|
G
|
I
|
Check and debug designs
|
4
|
Ii
|
1
|
Develop testing protocol
|
3
|
G
|
K
|
Identify critical performance levels
|
2
|
1
|
L
|
Assess and modify product components
|
6
|
I, K
|
M
|
Conduct capabilities assessment
|
12
|
L
|
N
|
Identify selection criteria
|
3
|
M
|
0
|
Develop RFQ
|
4
|
M
|
P
|
Develop production master schedule
|
S
|
N, 0
|
Q
|
Liaise with sales staff
|
1
|
P
|
R
|
Prepare product launch
|
3
|
Q
|
Exercise 2
Now, continue developing your Gantt chart with the rest of the information contained in the table above and create a complete activity network diagram for this project.
Exercise 3
Identify the critical path for the project shown in Exercise 1. How can you tell? Hint Click on the "Tracking Gantt" option.
Exercise 4
Suppose that we wished to incorporate lag relationships into a Remodeling an Appliance activity network. Consider the table shown below and the lag relationships noted. Develop an MS Project Gantt chart that demonstrates these lags.
Activity Duration Lag Relationship
A Wiring 6 None
B Plumbing 2 None
C HVAC 3 Wiring (Finish to Start), Plumbing (Finish to Finish)
D Interior Construction 6 HVAC (Start to Start)