Develop an in-depth schedule for your initial project based


Put components for Part 1 of assignment here:

Develop an in-depth schedule for your initial project based on the Work Breakdown Structure you have completed in Unit III. Please refer to the "INTEGRATED PROJECT: Developing the Project Schedule" Be sure to include-

1. An activity precedence diagram

2. An activity duration table

3. A network diagram and Gannt charts

Exercise 1

Suppose we have a complete activity predecessor table (shown below) and we wish to create a network diagram highlighting the activity sequence for this project. Using MS Project, enter the activities, their durations, and their predecessors for activities A through E. Note that all duration times are in days.

Project: Remodeling an Appliance

Activity

 

Duration

Predecessors

A

Conduct competitive analysis

3

 

B

Review field sales reports

2

 

C

Conduct tech capabilities assessment

5

 

D

Develop focus group data

2

A, B, C

E

Conduct telephone surveys

3

D

F

Identify relevant specification improvements

3

E

G

Interface with marketing staff

1

F

li

Develop engineering specifications

5

G

I

Check and debug designs

4

Ii

1

Develop testing protocol

3

G

K

Identify critical performance levels

2

1

L

Assess and modify product components

6

I, K

M

Conduct capabilities assessment

12

L

N

Identify selection criteria

3

M

0

Develop RFQ

4

M

P

Develop production master schedule

S

N, 0

Q

Liaise with sales staff

1

P

R

Prepare product launch

3

Q

Exercise 2

Now, continue developing your Gantt chart with the rest of the information contained in the table above and create a complete activity network diagram for this project.

Exercise 3

Identify the critical path for the project shown in Exercise 1. How can you tell? Hint Click on the "Tracking Gantt" option.

Exercise 4

Suppose that we wished to incorporate lag relationships into a Remodeling an Appliance activity network. Consider the table shown below and the lag relationships noted. Develop an MS Project Gantt chart that demonstrates these lags.

Activity                          Duration               Lag Relationship

A Wiring                             6                             None

B Plumbing                          2                             None

C HVAC                              3            Wiring (Finish to Start), Plumbing (Finish to Finish)

D Interior  Construction         6                     HVAC (Start to Start)