MATERIAL REQUIREMENTS PLANNING
Product A is an end item and is made from two units of B and four units of C. B is made of three units of D and two units of E. C Is made of two units of F and two units of E.
A has a lead time of one week, B, C, and E have lead times of two weeks, and D and F have lead times of three weeks.
a) Develop a time phased product structure (Draw in the back).
b) If 100 units of A are required in week 10 and 200 units in week 12 complete the gross requirement plan given below.