Develop a report that presents the activity schedule and


Case Problem- R. C. Coleman's

Managerial Report

Develop a report that presents the activity schedule and expected project completion time for the warehouse expansion project. Include a project network in the report. In addition take into consideration the following issues:

1. R. C. Coleman's top management established a required 40-week completion time for the project. Can this completion time be achieved? Include probability information in your discussion. What recommendations do you have if the 40-week completion time is required?

2. Suppose that management requests that activity times be shortened to provide an 80% chance of meeting the 40-week completion time. If the variance in the project completion time is the same as you found in part (1), how much should the expected project completion time be shortened to achieve the goal of an 80% chalice of com¬pletion within 40 weeks?

3. Using the expected activity times as the normal times and the following crashing in¬formation, determine the activity crashing decisions and revised activity schedule for the warehouse expansion project:

Activity

Crashed Activity Time
(weeks)

Cost($)

Normal

Crashed

A

4

1,000

1,900

B

7

1.000

1.800

C

2

1,500

2,700

D

8

2,000

3.200

E

7

5,000

8,000

F

4

3.000

4,100

G

5

8,000

10,250

H

4

5,000

6,400

I

4

10,000

12.400

J

3

4,000

4,400

K

3

5,000

5,500

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Develop a report that presents the activity schedule and
Reference No:- TGS0986941

Expected delivery within 24 Hours