Develop a network drawing for hill construction and


Case Study

Case Studies Southwestern University:

(A)* Southwestern University (SWU), a large state college in Stephenville, Texas, 30 miles southwest of the Dallas/Fort Worth metroplex, enrolls close to 20,000 students. In a typical town-gown relationship, the school is a dominant force in the small city, with more students during fall and spring than permanent residents.

A longtime football powerhouse, SWU is a member of the Big Eleven conference and is usually in the top 20 in college football rankings. To bolster its chances of reaching the elusive and long-desired number-one ranking, in 2003, SWU hired the legendary Bo Pitterno as its head coach.

One of Pitterno's demands on joining SWU had been a new stadium. With attendance increasing, SWU administrators began to face the issue head-on. After 6 months of study, much political arm wrestling, and some serious financial analysis, Dr. Joel Wisner, president of Southwestern University, had reached a decision to expand the capacity at its on-campus stadium.

* This integrated study runs throughout the text. Other issues facing Southwestern's football expansion include (B) forecasting game attendance (Chapter 4); (C) quality of facilities (Chapter 6); (D) break-even analysis for food services (Supplement 7 Web site); (E) location of the new stadium (Chapter 8 Web site); (F) inventory planning of football programs (Chapter 12 Web site); and (G) scheduling of campus security officers/staff for game days (Chapter 13).

Adding thousands of seats, including dozens of luxury skyboxes, would not please everyone. The influential Pitterno had argued the need for a first-class stadium, one with built-in dormitory rooms for his players and a palatial office appropriate for the coach of a... [continues]

1. Develop a network drawing for Hill Construction and determine the critical path. How long is the project expected to take?

2. What is the probability of finishing in 270 days?

3. If it is necessary to crash to 250 or 240 days, how would Hill do so, and at what costs? As noted in the case, assume the optimistic time estimates can be used as crash times.