Develop a network drawing for hill construction


Task:

Expansion of a football stadium to add 21000 seats including dozens of luxury boxes 270 days to complete with $10,000/day penalty for running late.

Questions: Develop a network drawing for Hill Construction and determine critical path. How long is the project expected to take

What is the probability of finishing in 270 days

If it were necessary to crash to 250 or 250 days how would you do so and at what cost (assume optimistic time estimates can be used as crash times)

Table with all needed figures are below.




Time Estimates (Days)







Activity Descriptions Prede Oppti Most Pessi Crash
    cessors mistic Likely mistic Cost/Days
A Bonding, insurance, tax struc   20 30 40 1500
B Foundation, Concrete Footings A 20 65 80 3500
C Upgrading skyboxes, seats A 50 60 100 4000
D Walkways, stairwells,eleavator C 30 50 100 1900
E Interior wiring, lathes B 25 30 35 9500
F Inspection approvals E 1 1 1 0
G Plumbing D,E 25 30 35 2500
H Painting G 10 20 30 2000
I Hardware/ AC/Metal works H 20 25 60 2000
J Tile, carpeting,windows H 8 10 12 6000
K Inspection  J 1 1 1 0
L Final detail work/cleanup L,K 20 25 60 4500

Solution Preview :

Prepared by a verified Expert
Basic Statistics: Develop a network drawing for hill construction
Reference No:- TGS01940343

Now Priced at $25 (50% Discount)

Recommended (91%)

Rated (4.3/5)