Develop a net material requirements plan


As the production schedules for an exercise equipment manufacturer, you are to schedule an order for 50 UltimaSteppers, which are to be shipped in week 8. Assume lot-for-lot ordering. Below is information about the steppers.

Lead

Item Time On Hand Components
Stepper 2 20 A(1), B(3), C(2)
A 1 10 D(1), F(2)
B 2 30 E(1), F(3)
C 3 10 D(2), E(3)
D 1 15
E 2 5
F 2 20

a) Develop a product structure.
b) Develop a time-phased structure.
c) Develop a net material requirements plan for F.