Develop a cost budgeted schedule based on the earliest


The following costs have been estimated for the activities in a project:

ACTIVITY

IMMEDIATE PREDECESSORS

TIME

TOTAL COST ($)

A

-

10

13400

B

-

5

12000

C

A

4

5800

D

B

7

10500

E

C,D

8

9600

F

C.D

4

11400

G

F

3

3660

 

a) Develop a cost budgeted schedule based on the earliest start time. Please keep one decimal place.

b) Develop a cost budgeted schedule based on the latest start time. Please keep one decimal place.