Develop a complete activity schedule based on the crashed


Norton Industries is installing a new computer system. The activities, the activity times, and the project network are as follows:

Activity

A

Time

3

Activity

E

Time

4

B

6

F

3

C

2

G

9

D

5

H

3

12_Critical Path.png

The critical path calculation shows B-D-E-F-H is the critical path, and the expected project completion time is 21 weeks. After viewing this information, management requested overtime be used to complete the project in 16 weeks. Thus, crashing of the project is necessary. The following information is relevant:

Activity

A

Normal

3

Crash

1

Normal

900

Crash

1700

B

6

3

2000

4000

C

2

1

500

1000

D

5

3

1800

2400

E

4

3

1500

1850

F

3

1

3000

3900

G

9

4

8000

9800

H

3

2

1000

2000

a. Formulate a linear programming model that can be used to make the crashing decisions for this project.

b. Solve the linear programming model and make the minimum cost crashing decisions. What is the added cost of meeting the 16-week completion time?

c. Develop a complete activity schedule based on the crashed activity times.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Develop a complete activity schedule based on the crashed
Reference No:- TGS01220212

Expected delivery within 24 Hours