Determining the production time for bookshelf model


Assignment:

Greenville Cabinets received a contract to produce speaker cabinets for a major s manufacturer. The contract calls for the production of 3300 bookshelf speakers and 4100 floor speakers over the next two months, with the following delivery schedule:

Model         Month 1  Month 2

Bookshelf     2100     1200
Floor           1500     2600

Greenville estimates that the production time for each bookshelf model is 0.7 hour and the production time for each floor model is 1 hour. The raw material costs are $10 for each bookshelf model and $12 for each floor model. Labor costs are S22 per hour using regular production time and $33 using overtime. Greenville has up to 2400 hours of regular production time available each month and up to 1000 additional hours of overtime available each month. If production for either cabinet exceeds demand in month 1, the cabinets can be stored at a cost of $5 per cabinet. For each product, determine the number of units that should be manufactured each month on regular time and on overtime to minimize total production and storage costs.

Request for Solution File

Ask an Expert for Answer!!
Marketing Management: Determining the production time for bookshelf model
Reference No:- TGS02967313

Expected delivery within 24 Hours