Determining sequence to minimize the total completion time


Assignment:

Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows:

Job Operation 1 (Hours) Operation 2 (Hours)
A 10 5
B 7 4
C 5 7
D 3 8
E 2 6
F 4 3

Determine a sequence that will minimize the total completion time for these jobs. Illustrate graphically.

Provide complete and step by step solution for the question and show calculations and use formulas.