Determining sequence of tasks and total time to complete it


Assignment:

A company is faced with seven tasks that have to be processed through two work centers. Assume work center I works continuously and that they wish to minimize idle time. Data appear below in hours. What is the sequence of tasks, and what is the total time to complete all tasks?

Task

Work Center I

Work Center II

A

2.58

3.47

B

1.66

5.84

C

2.71

2.41

D

5.52

1.99

E

3.38

7.62

F

5.22

1.73

G

2.89

1.11