Assignment:
A company is faced with seven tasks that have to be processed through two work centers. Assume work center I works continuously and that they wish to minimize idle time. Data appear below in hours. What is the sequence of tasks, and what is the total time to complete all tasks?
Task
|
Work Center I
|
Work Center II
|
A
|
2.58
|
3.47
|
B
|
1.66
|
5.84
|
C
|
2.71
|
2.41
|
D
|
5.52
|
1.99
|
E
|
3.38
|
7.62
|
F
|
5.22
|
1.73
|
G
|
2.89
|
1.11
|
Your answer must be typed, double-spaced, Times New Roman font (size 12), one-inch margins on all sides, APA format and also include references.