Assignment:
A company manufacturer needs help planning production for next year. Demand for its main product is expected to be,
Month
|
Demand Forecast
|
Month
|
Demand Forecast
|
Month
|
Demand Forecast
|
Month
|
Demand Forecast
|
Jan
|
1000
|
Apr
|
2000
|
Jul
|
5000
|
Oct
|
500
|
Feb
|
500
|
May
|
3000
|
Aug
|
3000
|
Nov
|
500
|
Mar
|
500
|
Jun
|
4000
|
Sep.
|
1000
|
Dec
|
3000
|
Given the following costs and demand forecast, test two strategies for meeting demand: (1) chase strategy with overtime or (2) 3000 units' level production from April through September, subcontracting production during the other months to meet demands. Explain which strategy is the best.
Costs and Other Information
|
Beginning workforce
|
8 workers
|
Holding cost
|
$0.5 per unit/month
|
Subcontracting capacity
|
Unlimited
|
Backordering cost
|
$10 per unit/month
|
Production rate per worker
|
250 units/month
|
Subcontracting Cost
|
$30 per unit
|
Regular wage rate
|
$15/hour
|
Overtime wage rate
|
$30/hour
|
Provide complete and step by step solution for the question and show calculations and use formulas.