Determine what predecessors need to be listed


Project Management Homework

Joe and Noël have just gotten engaged. Seeing as they are both business students, they thought that they'd try to plan out their wedding preparation as a project. Here's the WBS they've determined is necessary for a simple but elegant wedding. Assume all durations are deterministic. Although perhaps not realistic to real wedding planning, use the standard calendar in ProjectLibreor MS Project (activities occur on business days and non-holidays only, 8 hours working time).

Task ID

Task Name

Duration

Predecessor

1

Begin Wedding Planning (milestone)

0 days

---

2

Select Site&Date

3 wks

1

3

Hire Officiant

1 wk

2

4

Hire Caterers

2 wks

1

5

Pick Menu

4 days

4

6

Order Invitations

2 wks

2,5

7

Sent Invitations to Guests

1 wk

6

8

Collect RSVPs

6 wks

7

9

Tell Caterer headcount & Order food

1 wk

8

10

Shop for Wedding Gown

4 wks

1

11

Select Bridesmaids Dresses

4 wks

10

12

Bride goes on Diet

6 wks

10

13

Get Wedding Gown altered

2 wks

12

14

Get Bridemaids' Dresses altered

4 wks

11

15

Order Flowers

2 wks

11

16

Audition Mariachi Bands

3 wks

2

17

Select and Sign on Band

1 wk

16

18

Select Grooms Tux

2 days

10

19

Select Best Man& Usher's Tuxes

2 days

18

20

Wedding Day (milestone)

0 days

????

Based on the project you created, answer the following questions. Please note that each question is independent and not built upon each other.

a. If Joe and Noël start wedding planning on October 1, 2020, when is the wedding day?

b. What is the critical path? List all critical tasks in chronological order.

c. Will the critical path change if Noël decides she needs two extra weeks for the Bridal Diet? If yes, what is the new critical path and when should theweddingbe held?

d. Assume that band auditions take twice as long as expected. Does this affect the wedding day? If yes, when should the wedding be held?

e. If they want to get married on 2/14/2022, when do they have to start the wedding planning?

f. Determine what predecessors need to be listed to make sure everything is done by the wedding day without needlessly checking things? Noël is going to be nervous enough without having to check to see if each of the 18 tasks are complete at the end!

Format your homework according to the give formatting requirements:

a. The answer must be double spaced, typed, using Times New Roman font (size 12), with one-inch margins on all sides.

b. The response also includes a cover page containing the title of the homework, the course title, the student's name, and the date. The cover page is not included in the required page length.

c. Also include a reference page. The references and Citations should follow APA format. The reference page is not included in the required page length.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Determine what predecessors need to be listed