Question:
(WA EUP & cost assignment) Ro-Day-O Inc. manufactures belt buckles in a single-step production process. The following information is available for June2010:
|
|
Cost of
|
|
|
Whole Units
|
Material
|
Cost of Labor
|
Beginning work in process
|
200,000
|
$1,200,000
|
$1,728,000
|
Units started during period
|
1,000,000
|
7,800,000
|
9,612,000
|
Units in ending inventory
|
300,000
|
|
|
Beginning inventory units were 100 percent complete as to material and 80 percent complete as to labor. The ending inventory units were 100 percent complete as to material and 50 percent complete as to labor. Overhead is applied to production at the rate of 60 percent of direct labor cost.
a. Prepare a schedule to compute equivalent units of production by cost component assuming the weighted average method.
b. Determine the unit production costs for material and conversion.
c. Calculate the costs assigned to completed units and ending inventory for August2010.