Under a given chart team A standard details are 400 members at $12 per hour and its actual detail are 480 members at $ 10 per hour, team B standard details are 800 members at $4 per hour and its actual details are 720 members at $ 6 per hour. If the actual production was exactly equal to the budgeted production for 200 hours during that week. Evaluate labor mix variance