Bionic CO manufactures dresses in a small facility in San Jose, California Information about the production week is as follows:

Standard wage per hour                                   $10.80
Standard labor time per dress                           12 minutes
Standard number of yards of fabric per dress     3.7 yards
Standard price per yard of fabric                       $2.95
Actual price per yard of fabric                           $2.75
Actual yards of fabric used this week                 12,100 yards
Number of dresses made this week                   3,250
Actual wage per hour                                       $11.00
Actual hours worked this week                          700 hours

Required:

A) Determine the total DIRECT MATERIALS cost variance, B) the DM price variance, C) and the DM quantity variance. For full credit, show your work and indicate Favorable or Unfavorable along with your variance amount.

Solution Preview :

Prepared by a verified Expert
Microeconomics: Determine the total direct materials cost variance b the dm
Reference No:- TGS02347362

Now Priced at $25 (50% Discount)

Recommended (90%)

Rated (4.3/5)