A monthly demand for a part produced for an automotive final assembly plant is 16000units. There are 20 working days in February and the effective operating time of the plant is 900 min per day(two shifts). The fraction defect rate for the component is 0.017 and the automated machine that produces the part has an availability of 96%. Determine the take time for this part.