Pauline Found Manufacturing ismoving to kanbans to support its telephone switching board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed.
Setup Cost: $30
Annual Holding Cost: $110 per subassembly
Daily Production: 40 subassemblies
Annual Usage: 3,000 (50 weeks * 5 days each * daily usage of 12 subassemblies
Lead Time: 10 days
Safety Stock: 2 days production