Determine the rate variance and time variance


The following data relate to labor cost for production of 12,500 cellular phones:

Actual: 13,600 at $16.15 $219,640

Standard: 13,725 hours at $16.00 $219,600

Determine the rate variance, time variance, and total direct labor cost variance.