An investment project is expected to generate earnings before taxes (EBT) of $60,000 per year. Annual depreciation from the project is $30,000 and the firm’s tax rate is 40 percent. Determine the project’s annual net cash flows.
$48,000
$66,000
$36,000
$52,000