The following table ( attached )shows orders to be processed at a machine shop as of 8:00 a.m. Monday. The jobs have different operations they must go through. Processing times are in days. Jobs are listed in order of arrival. Determine the processing sequence at the first work center using each of these rules: FCFS and S/O.