An asphalt paving crew is used to pave a 500-foot by 300-foot parking lot. The parking lot will be paved in 12-foot-wide strips running the long (500-foot) direction. The machine paves 11 lineal feet of 12-foot-wide parking lot per minute. A single lift of asphalt will be used on the parking lot. After completing a pass, it takes the crew 10 minutes to turn the paving machine around and get ready for the next pass. The crew consists of a foreperson, six operators, and a laborer. Using a system efficiency of 50 minutes per hour, determine the number of labor hours required to place 1 lineal foot of parking lot 12 feet wide.