Valley Care Medical Center expects Projects X and Y to generate the following cash flows:
|
Givens (in '000s)
|
Years 0
|
1
|
2
|
3
|
4
|
5
|
1
|
Initial investment ($7,500)
|
|
|
|
|
|
2
|
Net operating cash flows for Project X
|
$7,000
|
$5,000
|
$3,000
|
$2,000
|
$1,500
|
3
|
Net operating cash flows for Project Y
|
$1,500
|
$2,000
|
$3,000
|
$5,000
|
$7,000
|
a. Determine the NPV for both projects using a cost of capital of 17 percent.
b. Determine the NPV for both projects using a cost of capital of 12 percent.
c. At a 12 percent discount rate, which project should be accepted? At a 17 percent discount rate, which project should be accepted? Explain.