Determine the npv for both projects


Castle Rock Medical Center expects Projects X and Y to generate the following cash flows:

NOCF = Net Operating Cash Flows

Givens

(thousands)

Years

0

1

2

3

4

5

Initial Investment

 

(6,500)

 

 

 

 

 

Project  X

NOCF

 

 

5,000

3,000

2,000

1,600

1,000

Project Y

NOCF

 

 

1,000

1,600

2,000

3,000

5,000

Discount rate for Part a

13%

 

 

 

 

 

 

Discount rate for Part b

8%

 

 

 

 

 

 

a. Determine the NPV for both projects using a cost of capital of 13%

b. Determine the NPV for both projects using a cost capital of 8%

c. At an 8% discount rate, which project should be accepted?

At a 13% discount rate, which project should be accepted? Explain.

Request for Solution File

Ask an Expert for Answer!!
Finance Basics: Determine the npv for both projects
Reference No:- TGS0551228

Expected delivery within 24 Hours