Determine the loosening costs in the following situation


21.Track-Type Tractors Dozing

Determine average hourly production of a D8N/8SU (Hydraulic with tilt

cylinder) coal, an average distance of 400m down a 15% grade, using a slot dozing technique. Estimated material weight is 1600 kg/Lm3. Material density =1392 kg/Lm3. Operator is average. Job efficiency is 50 min/hr (check the notes for production curve, table for correction factors).

Uncorrected maximum production     458 Lm3/hr

 

22.Track-Type Tractors Ripping

Determine the loosening costs in the following situation: Machine D11R Tractor with No. 11 single shank ripper in coal Rip spacing 1600mm

Ripper penetration 500mm Rip distance 150m

Rip time           4.32 minutes Manoeuvre time                        0.35 minutes

 

Seismic velocity          2500 m/s (assume this is a realistic value for coal, graphs available to check).

Working rate per hour                         $ 120

What is the effect of the seismic velocity of rock on dozer ripping operations?

 

23.Motor Grader

A Motor grader will travel at an average speed of 10km/hr along a haul road to clear the shoulder for a distance of 20km on one side. It is expected that proper clearing will require three passes, and that the machine has the usual efficiency factor of 0.6. Calculate the production expected from this grader performing this task.

 

24.Dragline

Rated Capacity of a Dragline Bucket

Calculate the rated capacity of a dragline bucket, given the following information:

Height at front = 2m

 Height at rear = 2.25m

Length at top = 5.9m

Length at bottom = 5.4m

Width of front top = 3m

Width of rear top = 3m

 Width of front base = 3m

Width of rear base = 3m

Factor for capacity loss due to bucket design = 0.20

 

25.Wheel Loader

Application                  Dozer pile less than 3m high dump to hopper

Production Required Material

Density

 

232.05 metric ton per hour poorly fragmented rock

1700kg/m3

Loading is constant with a hard level surface for loader manoeuvring. Show calculations and procedure to select an appropriate loader for this task.

Solution Preview :

Prepared by a verified Expert
Other Engineering: Determine the loosening costs in the following situation
Reference No:- TGS01006974

Now Priced at $35 (50% Discount)

Recommended (92%)

Rated (4.4/5)