Determine the longest queue the total delay from 8 am until


Vehicles arrive at a single park-entrance booth where a brochure is distributed. At 8 A.M. there are 20 vehicles in the queue and vehicles continue to arrive at the deterministic rate of λ(t) = 4.2 - 0.1t, where λ(t) is in vehicles per minute and t is in minutes after 8:00 A.M. From 8 A.M. until 8:10 A.M., vehicles are served at a constant deterministic rate of three per minute. Starting at 8:10 A.M., another brochure-distributing person is added and the brochure-service rate increases to six per minute (still at a single booth).

Assuming D/D/1 queuing, determine the longest queue, the total delay from 8 A.M. until the queue dissipates; and the wait time of the 40th vehicle to arrive.

Request for Solution File

Ask an Expert for Answer!!
Other Engineering: Determine the longest queue the total delay from 8 am until
Reference No:- TGS01525704

Expected delivery within 24 Hours