Determine the gross requirements


The master production schedule for two products, A and B, is shown below. To manufacture item A, four (4) units of component C are required. To manufacture item B, three (3) units of component C are required. Using this information, determine the gross requirements for component C to start week 1.

       Master Production Schedule: Wk 1

Product A

30

Product B

25

A)  195

B)  220

C)  155

D)  190

E)  None of the above