The master production schedule for two products, A and B, is shown below. To manufacture item A, four (4) units of component C are required. To manufacture item B, three (3) units of component C are required. Using this information, determine the gross requirements for component C to start week 1.
Master Production Schedule: Wk 1
|
Product A
|
30
|
Product B
|
25
|
A) 195
B) 220
C) 155
D) 190
E) None of the above